Protection class 3 | condensation-protected. The rapid expansion of Gerüstbau Heil urgently required more storage space. The challenge: the new warehouse had to be built as quickly and cost-effectively as possible. The solution: a partially used temporary building from HALTEC.

Space gain
800 m²

Width
20.00 m

Length
40.00 m

Side height
6.00 m

Ridge height
8.68 m

Snow load
0.90 kN/m²

Within a few weeks of the order being placed, the aluminium warehouse was erected on the existing gravel subsoil. Anchoring by ground pegs meant that no expensive and time-consuming foundation work was necessary. This meant that the 20.00 m wide and 40.00 m long hall could be assembled in just one working day. The partially used warehouse was clad with new trapezoidal sheet metal. This meant that the hall could be realised cost-effectively and still be visually appealing.

Equipment tailored to the utilisation

The "new" warehouse from Gerüstbau Heil offers exactly the equipment that the customer needs - no more and no less. Large roller shutter gates in the gable and side walls allow the scaffolding parts to be stored and retrieved quickly using forklift trucks. The gates also offer sufficient space for access with smaller lorries. Wall-strip windows in the two side walls provide natural lighting inside the hall.

Reference images and details

Efficient warehousing

The scaffolding parts can be stored and retrieved efficiently in the new warehouse at Gerüstbau Heil.

Large protected storage area

20.00 m span with a side height of 6.00 m - easy to realise thanks to the patented ALUFLEX.PLUS construction.

Safety stand

Anchored with ground pegs, the hall can withstand all forces even without foundations and stands securely in place.

Protection against condensation

In order to protect the stored scaffolding parts from dripping condensation, interior tarpaulins were installed under the roof cladding.

Natural lighting

Wall-strip windows provide natural light inside the hall.

Attractive exterior

The anthracite-coloured wall and roof cladding gives the hall a modern appearance.

Rent or buy temporary buildings?HALTEC BASIC

Rent

Full flexibility - minimal risk

There are many advantages to not purchasing a temporary building yourself: in addition to short-term space gains without high financial investment, you retain full flexibility with the option to purchase at a later date.

  • for short-term space gain
  • predictable monthly costs
  • no capital tied up – no loan
  • variable for conversion/expansion
  • optical condition: used

Discover the rental concept

Purchase

Customised & expandable

The longer you want to use your temporary building, the greater the advantages of buying it: the greatest possible customisability, coupled with high variability when converting or expanding.

  • variable for conversion/expansion
  • for longer service lives > 4 years
  • only new components
  • high investment costs

Well advised. HALTEC.

Building a hall raises many questions. Our online guide has detailed answers for you.

Find out how you can erect temporary buildings without foundations using soil nails. What you need to consider when obtaining approval for temporary buildings and which types of foundations are suitable if the temporary building is to be anchored with heavy-duty anchors. We also explain how temporary buildings can be moved on rails or attached without anchoring using ballast only.